APRIL 1, 2025
MOZAIKA VI
Occupancy permit obtained! Technical inspections by Clients are already underway at the investment site, and we are finalizing the last cleanup works.




NOVEMBER 18, 2024
MOZAIKA VI
Paving works on the investment site have been completed. Water and sewage installations as well as plastering have been completed inside the buildings. Preparations for floor screeding have begun.



JUNE 10, 2024
MOZAIKA VI
Work on the exterior facade has begun following the completion of the styrofoam insulation installation. Partition walls and electrical installations have already been completed inside the buildings.

DECEMBER 15, 2023
MOZAIKA V
Houses in Phase V have been handed over to the buyers. Finishing works are currently underway.
MOZAIKA VI
Windows have been installed in all buildings. Roof structures and their metal tile roofing have been completed.

SEPTEMBER 5, 2023
MOZAIKA V
Construction works on Phase V have been completed. The investment has obtained a final and binding occupancy permit. The handover of keys to the new owners has begun.
MOZAIKA VI
Work on the reinforced concrete structure has been completed. The estate has been connected to the electrical, water, sewage, and gas networks. The exterior walls of the ground floor have been completed.